Mashrou 101
6 Jul 2025

Sawaed Real Estate Al Rawdah 101 Project

69%Overall▲ +20% · vs previous visit

Engineering Report

The building's structural framework has been fully completed, along with the masonry work (red brick) for all floors. Interior finishing is currently underway, with a significant portion of the internal plastering completed. Installation of wall ceramics for kitchens and bathrooms has officially commenced, alongside ongoing electrical and plumbing installations.
Detected changes
Concrete Structure and Masonry100%

Full completion of the concrete structure, with red brick masonry reaching the roof and parapet levels.

Interior Finishes (Plastering)95%

Plastering works are at an advanced stage in rooms and internal corridors, with walls prepared for subsequent phases.

Ceramic Tiling Works100%

Commencement of wall ceramic installation in service areas (bathrooms/kitchens) using adhesive, with workers present during execution.

Electromechanical Installations90%

Installation of electrical conduits in ceilings and walls, along with the extension of primary water supply and drainage networks.

General Site Status95%

The site remains in the construction phase, with building materials (sand, cement, bricks) staged across floors and around the building perimeter.

Progress reading

Although the previously recorded percentage was 0%, the photos demonstrate tangible progress that has advanced beyond the structural phase into the initial finishing stages. The structure and masonry are complete, and plastering and tiling works have effectively begun.

vs previous visit

Compared to the previous site visit photos, we observe the project's transition from the exposed concrete structure stage to the completion of building works and the extensive commencement of internal plastering and tiling.

Expected next milestones

Completion of internal plastering, commencement of external facade works, completion of floor ceramic installation, and initiation of paint priming.

Progress

0%OverallAverage item progress
1/4 completeavg ▲ +42%
أعمال الخرسانات▲ +65%
0%
أعمال التشطيبnew
0%
أعمال الكهرباء▲ +30%
0%
أعمال السباكة▲ +30%
0%