Sawaed Real Estate Al Rawdah 101 Project
Engineering Report
Detected changes
Full completion of the concrete structure, with red brick masonry reaching the roof and parapet levels.
Plastering works are at an advanced stage in rooms and internal corridors, with walls prepared for subsequent phases.
Commencement of wall ceramic installation in service areas (bathrooms/kitchens) using adhesive, with workers present during execution.
Installation of electrical conduits in ceilings and walls, along with the extension of primary water supply and drainage networks.
The site remains in the construction phase, with building materials (sand, cement, bricks) staged across floors and around the building perimeter.
Progress reading
Although the previously recorded percentage was 0%, the photos demonstrate tangible progress that has advanced beyond the structural phase into the initial finishing stages. The structure and masonry are complete, and plastering and tiling works have effectively begun.
vs previous visit
Compared to the previous site visit photos, we observe the project's transition from the exposed concrete structure stage to the completion of building works and the extensive commencement of internal plastering and tiling.
Expected next milestones
Completion of internal plastering, commencement of external facade works, completion of floor ceramic installation, and initiation of paint priming.