Sawaed Real Estate Al Rawdah 101 Project
Engineering Report
Detected changes
Completion of pouring all columns and slabs for the typical floors, roof parapet, and elevator room, with some minor formwork remaining in the upper annex.
Completion of external wall construction and internal partitioning using red bricks for all floors, with additional brick stockpiles on the roof.
Appearance of electrical conduit coils (flexible pipes) inside the units, indicating the start of the electrical rough-in phase.
The site is enclosed by temporary fencing, with construction debris and timber stockpiles remaining around the building perimeter.
Progress reading
Although the previously recorded percentage was 0%, visual evidence shows highly advanced progress in the structural skeleton and masonry work, necessitating an update to the completion rates to reflect the conclusion of the structural phase.
vs previous visit
No previous visit available for comparison
Expected next milestones
Commencement of internal plastering works, completion of electrical and plumbing installations, and start of roof insulation.