Mashrou 101
21 Apr 2025

Sawaed Real Estate Al Rawdah 101 Project

49%OverallFirst visit — no previous comparison.

Engineering Report

The building's structural framework has been fully completed up to the roof annex, with significant progress in masonry work (red brick) for all typical floors, and the commencement of preliminary preparations for internal electrical wiring.
Detected changes
Concrete Structure100%

Completion of pouring all columns and slabs for the typical floors, roof parapet, and elevator room, with some minor formwork remaining in the upper annex.

Masonry Works100%

Completion of external wall construction and internal partitioning using red bricks for all floors, with additional brick stockpiles on the roof.

Utilities and Services90%

Appearance of electrical conduit coils (flexible pipes) inside the units, indicating the start of the electrical rough-in phase.

General Site95%

The site is enclosed by temporary fencing, with construction debris and timber stockpiles remaining around the building perimeter.

Progress reading

Although the previously recorded percentage was 0%, visual evidence shows highly advanced progress in the structural skeleton and masonry work, necessitating an update to the completion rates to reflect the conclusion of the structural phase.

vs previous visit

No previous visit available for comparison

Expected next milestones

Commencement of internal plastering works, completion of electrical and plumbing installations, and start of roof insulation.

Progress

0%OverallAverage item progress
1/4 complete
أعمال الخرساناتnew
0%
أعمال الخرساناتnew
0%
أعمال الكهرباءnew
0%
أعمال السباكةnew
0%

3D Model

Drone Photography

360 Video

On-site Photography

ShareChat on WhatsApp