Mashrou 101
27 Aug 2025

27 Aug 2025

85%Overall▲ +12% · vs previous visit

Main video

Engineering Report

A field visit was conducted to the project site on August 27, 2025, to document the current status as a baseline report. Visual inspection showed that the project has reached advanced stages in interior finishes and facade work, with the concrete structure fully completed for the main buildings within the scope of work.
Detected changes
Concrete Structure and Masonry100%

Full completion of the concrete structure for the buildings, with masonry (blockwork) appearing finished on the typical floors.

Exterior Facades95%

Installation of external scaffolding and commencement of external plastering and painting, with green safety netting covering the site.

Interior Finishes100%

Completion of interior plastering and installation of floor tiling (porcelain/ceramic) in rooms, with electrical wiring extensions visible from ceilings and walls.

Staircases and Utilities90%

Installation of marble/granite for the building's staircases, and ongoing plumbing and electrical installations in corridors and common areas.

Progress reading

Although the officially recorded completion rate is 0%, visual evidence indicates that the project has surpassed the concrete structure phase and is well into the final finishing stages (flooring, plastering, electrical installations). This necessitates an update to the completion percentages to reflect the actual field reality.

vs previous visit

No previous visit available for comparison

Expected next milestones

Installation of lighting fixtures, final coat painting, installation of sanitary ware, and removal of external scaffolding.

Progress

0%OverallAverage item progress
1/5 completeavg ▲ +12%
أعمال الحفر▲ +20%
0%
أعمال الخرسانات
0%
أعمال التشطيب▲ +25%
0%
أعمال الكهرباء▲ +10%
0%
أعمال السباكة▲ +5%
0%

Drone Photography

Ground Photography