27 Aug 2025
Main video
Engineering Report
Detected changes
Full completion of the concrete structure for the buildings, with masonry (blockwork) appearing finished on the typical floors.
Installation of external scaffolding and commencement of external plastering and painting, with green safety netting covering the site.
Completion of interior plastering and installation of floor tiling (porcelain/ceramic) in rooms, with electrical wiring extensions visible from ceilings and walls.
Installation of marble/granite for the building's staircases, and ongoing plumbing and electrical installations in corridors and common areas.
Progress reading
Although the officially recorded completion rate is 0%, visual evidence indicates that the project has surpassed the concrete structure phase and is well into the final finishing stages (flooring, plastering, electrical installations). This necessitates an update to the completion percentages to reflect the actual field reality.
vs previous visit
No previous visit available for comparison
Expected next milestones
Installation of lighting fixtures, final coat painting, installation of sanitary ware, and removal of external scaffolding.