Sawaed Real Estate Al Rawdah 102 Project
Engineering Report
Detected changes
Full completion of the concrete structure and red brick masonry for all floors, with external scaffolding currently in place.
Execution of cement plastering for internal walls in several residential units, reaching advanced stages.
Commencement and ongoing installation of wall ceramics in kitchens and bathrooms in various colors and patterns (grey, marble green, white).
Installation of flexible electrical conduits, switch boxes, and ventilation ducts in ceilings and walls.
Progress reading
Although the recorded data indicates 0% overall completion, field photos confirm that the project has surpassed the structural phase and is well into the finishing stage. There is a substantial visual transformation compared to the previous visit, particularly regarding plastering and ceramic works.
vs previous visit
Compared to the previous site visit photos (e.g., Photo 26), a transition is observed from the structural shell stage to the internal plastering and ceramic tiling phase, along with relative organization and cleaning of the internal work areas.
Expected next milestones
Completion of internal plastering, commencement of primer painting works, installation of suspended ceilings, and completion of external system installations.