Sawaed Real Estate Al Rawdah 102 Project
Main video
Engineering Report
Detected changes
Exterior cladding and facade painting are largely complete, with scaffolding remaining on some side sections.
Floor tiling, wall painting (primer/base coat), and installations for suspended ceilings and electrical systems are underway.
Installation of upper water tanks and piping is complete, while construction debris remains in the surrounding general site.
Window frames have been installed in most openings, with some units ready for installation on-site.
Progress reading
Although the recorded data indicates 0% overall completion, the photos reveal an advanced engineering reality exceeding 85% of structural and exterior finishing works, indicating a discrepancy between the administrative updates and the actual field progress.
vs previous visit
Compared to the previous photos (21-26), the work has progressed from the roof waterproofing stage (black bitumen) to the installation of tiles and water tanks, with significant advancement in interior painting works.
Expected next milestones
Installation of window glazing, installation of final sanitary and electrical fixtures, removal of external scaffolding, and general site cleaning.