Hay Al Rawdah 102 Project
24 Sept 2025

Sawaed Real Estate Al Rawdah 102 Project

93%Overall▲ +5% · vs previous visit

Main video

Engineering Report

The Al-Rawdah 102 project is in the advanced final finishing stages; the structural framework and exterior facade works are largely complete, while work continues on interior finishes (tiling, painting, electrical installations) and the installation of upper water tanks.
Detected changes
Exterior Facades95%

Exterior cladding and facade painting are largely complete, with scaffolding remaining on some side sections.

Interior Finishes90%

Floor tiling, wall painting (primer/base coat), and installations for suspended ceilings and electrical systems are underway.

Roof and General Site95%

Installation of upper water tanks and piping is complete, while construction debris remains in the surrounding general site.

Aluminum and Carpentry Works85%

Window frames have been installed in most openings, with some units ready for installation on-site.

Progress reading

Although the recorded data indicates 0% overall completion, the photos reveal an advanced engineering reality exceeding 85% of structural and exterior finishing works, indicating a discrepancy between the administrative updates and the actual field progress.

vs previous visit

Compared to the previous photos (21-26), the work has progressed from the roof waterproofing stage (black bitumen) to the installation of tiles and water tanks, with significant advancement in interior painting works.

Expected next milestones

Installation of window glazing, installation of final sanitary and electrical fixtures, removal of external scaffolding, and general site cleaning.

Progress

0%OverallAverage item progress
3/5 completeavg ▲ +6%
أعمال الحفر
0%
أعمال الخرسانات▲ +5%
0%
أعمال التشطيبnew
0%
أعمال الكهرباء▲ +5%
0%
أعمال السباكة▲ +15%
0%