Sawaed Real Estate Project Al Rawdah 102
Engineering Report
Detected changes
Completion of column and slab casting for all typical floors up to the annex, with formwork removed and the structure visually complete.
Completion of a significant portion of external walls and internal partitions using red blocks, including the installation of fixing angles and mesh at joints.
Commencement of internal plastering works, with walls on middle floors covered in cement plaster and stockpiles of sand and cement on-site.
Visible installation of flexible electrical conduits and switch box rough-ins within walls prior to plastering, along with some plumbing drainage extensions.
Progress reading
Although the report indicates a total completion rate of 0%, the photographs confirm that the project has surpassed the structural skeleton phase and entered the initial finishing stages (plastering and rough-ins), reflecting tangible on-site progress.
vs previous visit
Compared to the previous visit, the project has progressed from the pure structural framework stage to the building enclosure stage, with the commencement of internal plastering and utility installations.
Expected next milestones
Completion of internal plastering works, commencement of waterproofing for roofs and bathrooms, and the start of installing metal or wooden door frames.