Hay Al Rawdah 102 Project
6 Jul 2025

Sawaed Real Estate Project Al Rawdah 102

64%Overall▲ +15% · vs previous visit

Engineering Report

The structural framework of the building has been fully completed, with significant progress in masonry work (red brick) across all floors. Internal plastering (spraying and filling) has commenced on several levels, alongside the installation of initial electrical and plumbing rough-ins.
Detected changes
Concrete Structure100%

Completion of column and slab casting for all typical floors up to the annex, with formwork removed and the structure visually complete.

Masonry Works95%

Completion of a significant portion of external walls and internal partitions using red blocks, including the installation of fixing angles and mesh at joints.

Plastering and Primary Finishes90%

Commencement of internal plastering works, with walls on middle floors covered in cement plaster and stockpiles of sand and cement on-site.

Electromechanical Installations85%

Visible installation of flexible electrical conduits and switch box rough-ins within walls prior to plastering, along with some plumbing drainage extensions.

Progress reading

Although the report indicates a total completion rate of 0%, the photographs confirm that the project has surpassed the structural skeleton phase and entered the initial finishing stages (plastering and rough-ins), reflecting tangible on-site progress.

vs previous visit

Compared to the previous visit, the project has progressed from the pure structural framework stage to the building enclosure stage, with the commencement of internal plastering and utility installations.

Expected next milestones

Completion of internal plastering works, commencement of waterproofing for roofs and bathrooms, and the start of installing metal or wooden door frames.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +18%
أعمال الخرساناتnew
0%
أعمال التشطيب▲ +15%
0%
أعمال الكهرباء▲ +25%
0%
أعمال السباكة▲ +15%
0%