Hay Al Rawdah 102 Project
21 Apr 2025

Sawaed Real Estate Al Rawdah 102 Project

49%OverallFirst visit — no previous comparison.

Engineering Report

Work has commenced on the baseline report for the Al-Rawdah 102 project. The site is currently in an advanced stage of the concrete structure phase, with red and cement brickwork ongoing across various floors, alongside active stockpiling of essential materials.
Detected changes
Concrete Structure100%

Completion of column and slab casting (hollow block system) for several floors, with metal formwork and structural shoring remaining in some areas to ensure proper curing.

Masonry Works100%

Significant progress in internal and external wall construction using red clay and cement bricks, with architectural openings for windows and doors being executed.

Site and Material Storage95%

Availability of large quantities of red bricks, cement bags, sand, and timber across the project floors, with active labor presence on-site.

Progress reading

Although the officially recorded completion rate is 0%, visual evidence indicates significant progress in structural and masonry work. This necessitates an update to the project schedule to reflect the actual status on the ground.

vs previous visit

No previous visit available for comparison

Expected next milestones

Completion of remaining masonry work, commencement of initial electrical and plumbing installations, and preparation for plastering works.

Progress

0%OverallAverage item progress
0/4 complete
أعمال الخرسانةnew
0%
أعمال التشطيبnew
0%
أعمال الكهرباءnew
0%
أعمال السباكةnew
0%