Sawaed Real Estate Al Rawdah 102 Project
Engineering Report
Detected changes
Completion of column and slab casting (hollow block system) for several floors, with metal formwork and structural shoring remaining in some areas to ensure proper curing.
Significant progress in internal and external wall construction using red clay and cement bricks, with architectural openings for windows and doors being executed.
Availability of large quantities of red bricks, cement bags, sand, and timber across the project floors, with active labor presence on-site.
Progress reading
Although the officially recorded completion rate is 0%, visual evidence indicates significant progress in structural and masonry work. This necessitates an update to the project schedule to reflect the actual status on the ground.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of remaining masonry work, commencement of initial electrical and plumbing installations, and preparation for plastering works.