Sawaed 103
21 Apr 2025

Sawaed Real Estate Al Rawdah 103 Project

3%OverallFirst visit — no previous comparison.

Engineering Report

Concrete structure works for the project have commenced, with current efforts focused on preparing the ground floor ceiling. The site shows active carpentry and reinforced steel works, with the necessary heavy equipment present on-site.
Detected changes
Concrete Structure100%

Completion of ground floor column casting and commencement of formwork and reinforcement for the ground floor slab, with column starters visible for the next level.

Electrical and Plumbing Works95%

Installation of primary conduits (PVC pipes) within the ground floor slab prior to the casting process.

General Site100%

Site preparation with temporary fencing and signage, including the presence of a crane and designated reinforcement steel storage areas in the outer perimeter.

Progress reading

The visual progress aligns with the concrete completion rate (10%), as foundations and ground floor columns are finished, and work on the ceiling is underway. The electrical progress (2%) is reflected in the visible ceiling conduits.

vs previous visit

No previous visit available for comparison

Expected next milestones

Casting the concrete for the ground floor ceiling, followed by the commencement of carpentry and blacksmithing for the first-floor columns.

Progress

0%OverallAverage item progress
0/4 complete
Concrete Worksnew
0%
Finishing Worksnew
0%
Plumbing Worksnew
0%
Electrical Worksnew
0%

3D Tour

Drone Footage

360 Video

On-site Photography

ShareChat on WhatsApp