Sawaed Real Estate Al Rawdah 103 Project
Engineering Report
Detected changes
Completion of ground floor column casting and commencement of formwork and reinforcement for the ground floor slab, with column starters visible for the next level.
Installation of primary conduits (PVC pipes) within the ground floor slab prior to the casting process.
Site preparation with temporary fencing and signage, including the presence of a crane and designated reinforcement steel storage areas in the outer perimeter.
Progress reading
The visual progress aligns with the concrete completion rate (10%), as foundations and ground floor columns are finished, and work on the ceiling is underway. The electrical progress (2%) is reflected in the visible ceiling conduits.
vs previous visit
No previous visit available for comparison
Expected next milestones
Casting the concrete for the ground floor ceiling, followed by the commencement of carpentry and blacksmithing for the first-floor columns.