Sawaed Real Estate Al Rawdah 103 Project
Main video
Engineering Report
Detected changes
Significant completion of exterior plastering for the facades, along with the installation of rooftop water tanks and full tiling of the roof floor.
Continuation of interior plastering and floor tiling in several apartments, with the commencement of initial painting (priming) for selected walls and ceilings.
Installation of electrical wiring within wall boxes and fitting of plumbing fixtures (valves) in bathrooms over the tiling.
Progress reading
The visual evidence aligns with the reported completion rates; tiling and initial painting works reflect finishing progress of approximately 45%, while wiring and valve installations show electrical and plumbing works exceeding 60%.
vs previous visit
Compared to the previous visit photos, it is noted that external scaffolding has been removed from most facades, the installation of upper water tanks is complete, and there is significant progress in the interior tiling of the apartments.
Expected next milestones
Completion of electrical sockets and switches installation, commencement of sanitary ware installation, and finishing of the final paint coats.