Sawaed 103
8 Feb 2026

Sawaed Real Estate Al Rawdah 103 Project

68%Overall-26% · vs previous visit

Main video

Engineering Report

The Sawaed 103 project was visited on 2026-02-08, with a total completion rate of 68%. Work is currently focused on advanced interior finishing stages and final service installations, following the full completion of the concrete structure.
Detected changes
Exterior Facades and Rooftop95%

Significant completion of exterior plastering for the facades, along with the installation of rooftop water tanks and full tiling of the roof floor.

Interior Finishing Works90%

Continuation of interior plastering and floor tiling in several apartments, with the commencement of initial painting (priming) for selected walls and ceilings.

Plumbing and Electrical Works85%

Installation of electrical wiring within wall boxes and fitting of plumbing fixtures (valves) in bathrooms over the tiling.

Progress reading

The visual evidence aligns with the reported completion rates; tiling and initial painting works reflect finishing progress of approximately 45%, while wiring and valve installations show electrical and plumbing works exceeding 60%.

vs previous visit

Compared to the previous visit photos, it is noted that external scaffolding has been removed from most facades, the installation of upper water tanks is complete, and there is significant progress in the interior tiling of the apartments.

Expected next milestones

Completion of electrical sockets and switches installation, commencement of sanitary ware installation, and finishing of the final paint coats.

Progress

0%OverallAverage item progress
1/4 completeavg ▼ -26%
Concrete Works
0%
Finishing Works-40%
0%
Plumbing Works-30%
0%
Electrical Works-35%
0%