Sawaed Real Estate Al Rawdah 103 Project

13%Overall▲ +10% · vs previous visit

Engineering Report

The project has shown significant progress in the concrete structure, with the commencement of initial finishing and masonry works. Casting of the typical floor slabs has been completed, and the project has moved to the carpentry and reinforcement phase for the next floor's columns, coinciding with the arrival of casting equipment and construction materials on-site.
Detected changes
Concrete Structure100%

Completion of roof slab casting for lower floors and commencement of formwork and reinforcement for the new floor columns, with the concrete pump present on-site.

Masonry and Finishing Works95%

Commencement of wall construction using red clay bricks on floors where formwork has been stripped, with additional brick supplies delivered to the site.

Utilities and Services90%

Visible plumbing installations (drainage pipes) and electrical rough-ins within the ceilings and columns currently under construction.

Site Layout and Logistics100%

Presence of concrete mixer trucks and an Everdigm pump, with the staging area organized and project signage updated.

Progress reading

The photos align with the surge in concrete completion from 10% to 30%, clearly showing the transition from the slab formwork stage (in the previous visit) to a multi-story structure with standing columns. The images also support the start of finishing works (7%) through the appearance of red block masonry walls.

vs previous visit

Compared to the previous site visit photos (21-24), the project has progressed from the reinforcement stage of the ground/first-floor slabs to the construction of additional floors and the commencement of masonry work, reflecting a high pace of work over the past three weeks.

Expected next milestones

Casting the columns for the current floor, continuing internal partition masonry work, and starting service installations for the structurally completed floors.

Progress

0%OverallAverage item progress
0/4 completeavg ▲ +10%
Concrete Works▲ +20%
0%
Finishing Works▲ +7%
0%
Plumbing Works▲ +5%
0%
Electrical Works▲ +6%
0%