Sawaed Real Estate Al Rawdah 103 Project
Engineering Report
Detected changes
Completion of roof slab casting for lower floors and commencement of formwork and reinforcement for the new floor columns, with the concrete pump present on-site.
Commencement of wall construction using red clay bricks on floors where formwork has been stripped, with additional brick supplies delivered to the site.
Visible plumbing installations (drainage pipes) and electrical rough-ins within the ceilings and columns currently under construction.
Presence of concrete mixer trucks and an Everdigm pump, with the staging area organized and project signage updated.
Progress reading
The photos align with the surge in concrete completion from 10% to 30%, clearly showing the transition from the slab formwork stage (in the previous visit) to a multi-story structure with standing columns. The images also support the start of finishing works (7%) through the appearance of red block masonry walls.
vs previous visit
Compared to the previous site visit photos (21-24), the project has progressed from the reinforcement stage of the ground/first-floor slabs to the construction of additional floors and the commencement of masonry work, reflecting a high pace of work over the past three weeks.
Expected next milestones
Casting the columns for the current floor, continuing internal partition masonry work, and starting service installations for the structurally completed floors.