Sawaed 103
6 Jul 2025

Sawaed Real Estate Al Rawdah 103 Project

59%Overall▲ +13% · vs previous visit

Main video

Engineering Report

The Sawaed 103 project was visited on July 6, 2025, showing the project at an advanced stage of masonry work for the structural frame. Most major concrete elements have been poured, with red brick wall construction ongoing across various floors. Activity in preliminary internal installations is noted, while completion rates remain consistent with the previous report, indicating a short documentation period or a focus on details that have not yet significantly altered the overall percentages.
Detected changes
Concrete Structure95%

Completion of column and slab pouring for typical floors up to the roof annex, with the stairwell and elevator room structurally complete.

Masonry Works90%

Ongoing construction of internal and external partitions using red bricks, with work reaching the upper floors while window openings remain.

Site and Facades95%

External facades are still in the structural stage (red brick) and external plastering has not yet commenced. The site is enclosed by safety fencing with brick materials staged on-site.

Progress reading

The visual evidence aligns with the concrete completion rate (80%), as the structure is nearly complete except for minor structural finishes. Finishing works (45%) are clearly visible in the progress of masonry (blockwork), which is a fundamental part of this stage. Plumbing and electrical works (25-35%) are evident through the initial installations within the walls and ceilings.

vs previous visit

Comparing current photos with the previous visit (photos 21 to 26), the project has progressed from the final roof slab casting stage and the presence of the concrete pump (visible in the previous visit) to the intensification of red brick masonry work across all floors and the dismantling of the upper roof formwork.

Expected next milestones

Commencement of internal plastering works, completion of plumbing and electrical installations (first fix), and the start of waterproofing for roofs and bathrooms.

Progress

0%OverallAverage item progress
1/4 completeavg ▲ +13%
Concrete Works▲ +20%
0%
Finishing Works
0%
Plumbing Works▲ +30%
0%
Electrical Works
0%