Sawaed Real Estate Al Hamra 104 Project
Engineering Report
Detected changes
Ongoing concrete pouring for the slab, with the completion of upper and lower reinforcement steel bars and the installation of red hollow blocks (Hordi).
Visible plumbing pipes (PVC) and electrical conduits integrated within the slab reinforcement prior to concrete casting.
Presence of concrete pumps and ready-mix trucks on-site to complete the pouring process, utilizing artificial lighting for night shifts.
Progress reading
Although the report indicates an overall completion rate of 0%, the images confirm that the excavation and foundation stages have been surpassed, with the actual pouring of the initial floor slabs underway. This indicates tangible progress that has not yet been reflected in the estimated percentages.
vs previous visit
Compared to the photos from the previous visit (photos 21 to 26), we observe the project's transition from the roof reinforcement preparation stage to the actual concrete pouring stage. Previous photos showed the roof covered only with steel reinforcement without the presence of pumps or poured concrete.
Expected next milestones
Dismantling the concrete roof formwork, commencing column works for the next floor, and starting masonry (block) works for the poured floors.