Sawaed 104
18 Aug 2025

Sawaed Real Estate Al Hamra 104 Project

23%Overall▲ +17% · vs previous visit

Engineering Report

The images show significant progress on-site, with reinforced concrete pouring currently underway for a floor slab (likely the basement or ground floor) using mobile concrete pumps during the evening. Reinforcement work, hollow block installation, and plumbing and electrical rough-ins were completed prior to the start of the pour.
Detected changes
Concrete Structure100%

Ongoing concrete pouring for the slab, with the completion of upper and lower reinforcement steel bars and the installation of red hollow blocks (Hordi).

Electromechanical Installations95%

Visible plumbing pipes (PVC) and electrical conduits integrated within the slab reinforcement prior to concrete casting.

Site Logistics and Equipment100%

Presence of concrete pumps and ready-mix trucks on-site to complete the pouring process, utilizing artificial lighting for night shifts.

Progress reading

Although the report indicates an overall completion rate of 0%, the images confirm that the excavation and foundation stages have been surpassed, with the actual pouring of the initial floor slabs underway. This indicates tangible progress that has not yet been reflected in the estimated percentages.

vs previous visit

Compared to the photos from the previous visit (photos 21 to 26), we observe the project's transition from the roof reinforcement preparation stage to the actual concrete pouring stage. Previous photos showed the roof covered only with steel reinforcement without the presence of pumps or poured concrete.

Expected next milestones

Dismantling the concrete roof formwork, commencing column works for the next floor, and starting masonry (block) works for the poured floors.

Progress

0%OverallAverage item progress
1/5 completeavg ▲ +17%
أعمال الحفر▲ +80%
0%
أعمال الخرسانات▲ +7%
0%
أعمال التشطيب
0%
أعمال الكهرباء
0%
أعمال السباكة
0%

3D Visualization

Drone Cinematography