Sawaed Real Estate Al Hamra 104 Project
Engineering Report
Detected changes
Ongoing concrete slab pouring using pump equipment, along with the preparation of reinforcement steel and MEP (plumbing and electrical) conduits within the slabs.
Commencement and execution of internal and external wall masonry using red clay bricks and insulated cement blocks, including the framing of door and window openings.
Presence of pouring equipment (mixers and pumps) on-site, with work continuing during evening shifts to ensure timely completion.
Progress reading
The project has effectively moved past the ground level stage, with images clearly showing the completion of structural concrete for several floors and the commencement of internal partitioning (masonry). This indicates an accelerated pace of work compared to the previous report, which recorded no items.
vs previous visit
Compared to previous images, the site has progressed from the excavation or initial foundation stage to the emergence of a standing structure several stories high, with the commencement of brickwork that was not previously present.
Expected next milestones
Completion of the remaining ceiling slabs, finishing masonry work for all floors, and the start of plastering as well as mechanical and electrical rough-ins.