Sawaed 104
8 Dec 2025

Sawaed Real Estate Al Hamra 104 Project

24%Overall▲ +1% · vs previous visit

Engineering Report

Significant progress has been observed in the Sawaed 104 project, as work has transitioned from the foundation stage to the concrete structure and masonry phase. Concrete slab pouring is currently being carried out at night, in parallel with the execution of internal and external wall construction using red and cement bricks on the floors where formwork has been removed.
Detected changes
Concrete Structure100%

Ongoing concrete slab pouring using pump equipment, along with the preparation of reinforcement steel and MEP (plumbing and electrical) conduits within the slabs.

Masonry Works100%

Commencement and execution of internal and external wall masonry using red clay bricks and insulated cement blocks, including the framing of door and window openings.

General Site95%

Presence of pouring equipment (mixers and pumps) on-site, with work continuing during evening shifts to ensure timely completion.

Progress reading

The project has effectively moved past the ground level stage, with images clearly showing the completion of structural concrete for several floors and the commencement of internal partitioning (masonry). This indicates an accelerated pace of work compared to the previous report, which recorded no items.

vs previous visit

Compared to previous images, the site has progressed from the excavation or initial foundation stage to the emergence of a standing structure several stories high, with the commencement of brickwork that was not previously present.

Expected next milestones

Completion of the remaining ceiling slabs, finishing masonry work for all floors, and the start of plastering as well as mechanical and electrical rough-ins.

Progress

0%OverallAverage item progress
1/5 completeavg ▲ +1%
أعمال الحفر
0%
أعمال الخرسانات
0%
أعمال التشطيب▲ +3%
0%
أعمال الكهرباء
0%
أعمال السباكة
0%

3D Visualization

360 Video

Drone Footage

On-site Photography

ShareChat on WhatsApp