Sawaed Real Estate Al Hamra 104 Project
Engineering Report
Detected changes
Completion of the blinding layer and commencement of reinforcement for the concrete raft foundation across the entire site area, with column starter bars visible and formwork prepared for elevators and service shafts.
Presence of two concrete pumps and mixing trucks on-site in preparation for the pouring process, along with organized construction materials and stockpiling of reinforcement steel and timber.
Installation of temporary site fencing, including project identification boards and final architectural designs.
Progress reading
The images show significant progress exceeding the reported 5% completion for excavation works. The site has effectively moved into the concrete reinforcement phase, which explains the notable advancement between the previous and current site visits.
vs previous visit
Compared to the previous site visit photo (the last image), the work has progressed from the initial excavation stage and the presence of heavy equipment (excavator) to the advanced structural foundation stage, including steel reinforcement laying and preparation for pouring.
Expected next milestones
Pouring reinforced concrete for the raft foundation, followed by the commencement of formwork and reinforcement for the ground floor/basement columns.