Sawaed 104
28 Jun 2025

Sawaed Real Estate Al Hamra 104 Project

6%Overall▲ +5% · vs previous visit

Engineering Report

The project has transitioned from the excavation phase to the structural foundation stage. Work is currently underway to prepare the reinforcement steel for the raft foundation, with concrete pumps on-site to commence pouring operations.
Detected changes
Concrete Structure100%

Completion of the blinding layer and commencement of reinforcement for the concrete raft foundation across the entire site area, with column starter bars visible and formwork prepared for elevators and service shafts.

General Site95%

Presence of two concrete pumps and mixing trucks on-site in preparation for the pouring process, along with organized construction materials and stockpiling of reinforcement steel and timber.

Signage100%

Installation of temporary site fencing, including project identification boards and final architectural designs.

Progress reading

The images show significant progress exceeding the reported 5% completion for excavation works. The site has effectively moved into the concrete reinforcement phase, which explains the notable advancement between the previous and current site visits.

vs previous visit

Compared to the previous site visit photo (the last image), the work has progressed from the initial excavation stage and the presence of heavy equipment (excavator) to the advanced structural foundation stage, including steel reinforcement laying and preparation for pouring.

Expected next milestones

Pouring reinforced concrete for the raft foundation, followed by the commencement of formwork and reinforcement for the ground floor/basement columns.

Progress

0%OverallAverage item progress
0/5 completeavg ▲ +5%
Excavation Works▲ +15%
0%
Concrete Works▲ +8%
0%
Finishing Works
0%
Electrical Works
0%
Plumbing Works
0%

3D Visualization

Drone Footage

On-site Photography

ShareChat on WhatsApp