16 Jul 2026
Main video
Engineering Report
Detected changes
Completion of concrete slab pouring for all floors, including roof rooms, and removal of most structural formwork.
Completion of interior and exterior wall construction, and commencement of plastering for walls and ceilings, with cement base layers visible.
Installation of external scaffolding covered with green safety netting to begin external plastering and painting works.
Installation of vertical drainage pipes and supply lines, along with the installation of electrical boxes and flexible conduits within walls and ceilings.
Progress reading
The images align with the surge in completion rates, particularly in the concrete works which rose from 15% to 60%, as evidenced by the structural completion. The photos also support the start of finishing works (30%) through the observation of plastering activities and the staging of materials, such as cement bags, on-site.
vs previous visit
Compared to the previous visit photos (21-26), the project has progressed from the stage of casting first-floor columns and active formwork to the completed structural shell phase, with the commencement of cladding and internal utility works.
Expected next milestones
Completion of internal plastering works, commencement of window aluminum frame installation, and the start of waterproofing works for roofs and bathrooms.