Sawaed Real Estate Al Hamra 105 Project
Main video
Engineering Report
Detected changes
Completion of casting columns and slabs for typical floors, with ongoing formwork and preparations for casting additional upper floors.
Execution of internal and external wall masonry using red clay bricks and cement blocks across multiple floors.
Organization of the site perimeter and stockpiling of construction materials (bricks) within and adjacent to the structural frame.
Progress reading
Although the percentages recorded in the report indicate 0%, current field photos show tangible physical progress in concrete and masonry works. This reflects a discrepancy between the recorded data and the visual reality, which indicates that the excavation and foundation stages have been fully surpassed.
vs previous visit
The difference is radical; previous photos (21-26) showed the site as vacant land (parking lot/undeveloped land), whereas current visit photos show a multi-story building in the structural framing stage.
Expected next milestones
Completion of pouring the remaining floors, commencement of electrical and mechanical (plumbing) rough-ins within the walls, and the start of plastering works.