Sawaed 105
6 May 2026

Sawaed Real Estate Al Hamra 105 Project

36%Overall▲ +8% · vs previous visit

Main video

Engineering Report

Significant progress has been observed on-site, as the project has advanced from vacant land in the previous visit to an advanced stage of the concrete structure and masonry work. The structural frame is currently erected for several floors, with intensive commencement of red and cement brickwork.
Detected changes
Concrete Structure100%

Completion of casting columns and slabs for typical floors, with ongoing formwork and preparations for casting additional upper floors.

Masonry Works100%

Execution of internal and external wall masonry using red clay bricks and cement blocks across multiple floors.

General Site95%

Organization of the site perimeter and stockpiling of construction materials (bricks) within and adjacent to the structural frame.

Progress reading

Although the percentages recorded in the report indicate 0%, current field photos show tangible physical progress in concrete and masonry works. This reflects a discrepancy between the recorded data and the visual reality, which indicates that the excavation and foundation stages have been fully surpassed.

vs previous visit

The difference is radical; previous photos (21-26) showed the site as vacant land (parking lot/undeveloped land), whereas current visit photos show a multi-story building in the structural framing stage.

Expected next milestones

Completion of pouring the remaining floors, commencement of electrical and mechanical (plumbing) rough-ins within the walls, and the start of plastering works.

Progress

0%OverallAverage item progress
1/5 completeavg ▲ +10%
Excavation Worksnew
0%
Concrete Works▲ +20%
0%
Finishing Works▲ +10%
0%
Electrical Works▲ +5%
0%
Plumbing Works▲ +5%
0%