Sawaed Al Hamra 105 Real Estate Project
Main video
Engineering Report
Detected changes
The concrete roof slab casting is fully complete, showing the staircase and skylight openings, with steel column rebars protruding for the next floor.
Relative cleaning of the slab surface from casting debris, with some timber, manual equipment, and the casting hose remaining on-site.
Progress reading
The images demonstrate tangible progress in the concrete works, transitioning from the column formwork and reinforcement stage (observed in the previous visit) to the completion of the roof slab casting. This indicates that the progress has surpassed the 0% completion rate for concrete works mentioned in the paper report.
vs previous visit
Compared to the previous photos (13-18), which only showed the column formwork, the current visit reveals that the slab casting is fully complete, the column formwork has been removed, and the post-slab casting phase has commenced.
Expected next milestones
Stripping of the slab formwork and the commencement of carpentry and reinforcement work for the upper floor columns.