Sawaed 105
16 Oct 2025

Sawaed Real Estate Al Hamra 105 Project

22%OverallFirst visit — no previous comparison.

Main video

Engineering Report

The concrete raft foundation has been successfully poured for the entire project area, with the commencement of column reinforcement work and general site preparation. The images show the completion of the foundation phase and the start of preparing the vertical structure for the ground floor.
Detected changes
Concrete Structure100%

Completion of the reinforced concrete raft foundation pouring, with vertical column starter bars visible and distributed according to the structural plan.

Site Layout and Storage95%

Installation of the temporary perimeter fence, storage of reinforcement steel, timber, and cement blocks, along with a plastic water tank for site utility use.

Excavation and Backfilling100%

Full completion of excavation works reaching the foundation pouring level, with shoring walls surrounding the site.

Progress reading

Although the officially recorded progress is 0%, visual evidence confirms the completion of the excavation and foundation (raft) stages. This is a critical milestone that paves the way for the immediate start of the ground floor columns.

vs previous visit

No previous visit available for comparison

Expected next milestones

Carpentry and reinforcement for ground floor columns, followed by the commencement of foundation waterproofing.

Progress

0%OverallAverage item progress
1/5 complete
Excavation Worksnew
0%
Concrete Worksnew
0%
Finishing Worksnew
0%
Electrical Worksnew
0%
Plumbing Worksnew
0%