Sawaed Real Estate Al Rawdah 106 Project
Main video
Engineering Report
Detected changes
Completion of the ground floor slab casting and commencement of column formwork and ceiling scaffolding preparation, with vertical reinforcement bars clearly visible.
Installation of the external metal perimeter fencing (corrugated sheets) around the project site and mounting of the official project information board.
Execution of internal staircase formwork, reinforced with wooden and metal scaffolding supports.
Progress reading
Although the numerical data indicates 0%, current site photos confirm that the project has moved past the excavation and foundation stages, with the actual commencement of concrete structural elements above ground level, reflecting tangible progress in construction works.
vs previous visit
تظهر صور الزيارة السابقة (21-26) أن الموقع كان في مرحلة صب اللبشة الخرسانية مع بروز حديد تسليح الأعمدة فقط، بينما تظهر صور الزيارة الحالية (1-20) ارتفاع الهيكل الخرساني وبدء أعمال النجارة المكثفة للأعمدة والأسقف.
Expected next milestones
صب أعمدة الدور الأرضي، البدء في تسليح سقف الدور الأرضي، وأعمال مباني الدور الأرضي.