Sawaed Real Estate Al Rawdah 106 Project
Main video
Engineering Report
Detected changes
Completion of the blinding concrete pouring, with column and neck reinforcement starters visible and distributed according to the structural plan, along with some wooden formwork for the footings.
The site is enclosed by a temporary metal fence, with stockpiles of reinforcement steel and timber observed, and a general cleanliness of the poured surface.
Progress reading
Although the report indicates 0% overall completion, the photos demonstrate actual progress in the foundation stage; the excavation phase has been completed, and steel and formwork activities have begun over the poured blinding layer.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of reinforcement and formwork for footings, pouring of reinforced concrete for foundations, and commencement of footing insulation works.