Sawaed 106
12 Jan 2026

Sawaed Real Estate Al Rawdah 106 Project

22%OverallFirst visit — no previous comparison.

Main video

Engineering Report

The blinding concrete layer has been poured across the entire site area, with the commencement of steel reinforcement for columns and necks, alongside the preparation of formwork for various structural elements at the foundation level.
Detected changes
Concrete Structure100%

Completion of the blinding concrete pouring, with column and neck reinforcement starters visible and distributed according to the structural plan, along with some wooden formwork for the footings.

General Site95%

The site is enclosed by a temporary metal fence, with stockpiles of reinforcement steel and timber observed, and a general cleanliness of the poured surface.

Progress reading

Although the report indicates 0% overall completion, the photos demonstrate actual progress in the foundation stage; the excavation phase has been completed, and steel and formwork activities have begun over the poured blinding layer.

vs previous visit

No previous visit available for comparison

Expected next milestones

Completion of reinforcement and formwork for footings, pouring of reinforced concrete for foundations, and commencement of footing insulation works.

Progress

0%OverallAverage item progress
1/5 complete
Excavation Worksnew
0%
Concrete Worksnew
0%
Finishing Worksnew
0%
Electrical Worksnew
0%
Plumbing Worksnew
0%