107 WAREEF AL-SALAMA
28 Sept 2025

Sawaed Real Estate Al Salama 107 Project

4%OverallFirst visit — no previous comparison.

Main video

Engineering Report

The site was visited on September 28, 2025, revealing that the project is in its very early stages. Current work is entirely focused on demolition and debris removal of pre-existing buildings and land preparation, with heavy machinery present on-site to begin leveling works.
Detected changes
Site Overview and Demolition Works100%

Demolition of previous structures is complete, with large concrete masses accumulated. Debris removal and natural ground leveling operations have commenced.

Equipment and Machinery100%

Presence of a Shantui hydraulic excavator equipped with a breaker attachment and occasionally a bucket for breaking and loading operations.

Fencing and Perimeter95%

The site is enclosed by temporary fencing and existing adjacent buildings, with remnants of old walls currently being removed or secured.

Progress reading

Visual observations align with the reported completion rate (0%) for the structural framework, as the project is still in the 'Site Preparation' phase. Primary excavation works and concrete pouring have not yet commenced.

vs previous visit

No previous visit available for comparison

Expected next milestones

Debris removal completed, excavation works initiated to reach the required level, and site caravans delivered.

Progress

0%OverallAverage item progress
0/5 complete
Excavation Worksnew
0%
Concrete Worksnew
0%
Finishing Worksnew
0%
Electrical Worksnew
0%
Plumbing Worksnew
0%