Sawaed Real Estate Al Salama 107 Project
Main video
Engineering Report
Detected changes
Demolition of previous structures is complete, with large concrete masses accumulated. Debris removal and natural ground leveling operations have commenced.
Presence of a Shantui hydraulic excavator equipped with a breaker attachment and occasionally a bucket for breaking and loading operations.
The site is enclosed by temporary fencing and existing adjacent buildings, with remnants of old walls currently being removed or secured.
Progress reading
Visual observations align with the reported completion rate (0%) for the structural framework, as the project is still in the 'Site Preparation' phase. Primary excavation works and concrete pouring have not yet commenced.
vs previous visit
No previous visit available for comparison
Expected next milestones
Debris removal completed, excavation works initiated to reach the required level, and site caravans delivered.