Sawaed 108
11 Jul 2026

11 Jul 2026

6%Overall▲ +4% · vs previous visit

Main video

Engineering Report

The project has transitioned from the vacant land stage to the commencement of the building's concrete structure. Current works are focused on the reinforcement and formwork for the ground floor columns and concrete walls following the completion of the foundation works.
Detected changes
Concrete Structure100%

Concrete columns and shear walls are currently under construction, with extensive formwork and reinforcement activities across the entire site area.

General Site95%

The site has been fully cleared and prepared, with construction materials, timber, and small cranes on-site to facilitate work, and the plot boundaries clearly demarcated.

Progress reading

The images are consistent with the recorded 5% completion rate for concrete works, reflecting the beginning of the vertical structure (columns). They also show the progress of excavation and foundation works that preceded this stage, which have reached 25%.

vs previous visit

The difference is substantial; during the previous visit, the land was completely vacant (raw land) with no construction activity, whereas the current visit shows the completion of foundations and the commencement of vertical element casting.

Expected next milestones

Casting of ground floor columns, and commencement of formwork and reinforcement for the ground floor ceiling.

Progress

0%OverallAverage item progress
0/5 completeavg ▲ +4%
Excavation Works▲ +15%
0%
Concrete Works▲ +5%
0%
Finishing Works
0%
Electrical Works
0%
Plumbing Works
0%