11 Jul 2026
Main video
Engineering Report
Detected changes
Concrete columns and shear walls are currently under construction, with extensive formwork and reinforcement activities across the entire site area.
The site has been fully cleared and prepared, with construction materials, timber, and small cranes on-site to facilitate work, and the plot boundaries clearly demarcated.
Progress reading
The images are consistent with the recorded 5% completion rate for concrete works, reflecting the beginning of the vertical structure (columns). They also show the progress of excavation and foundation works that preceded this stage, which have reached 25%.
vs previous visit
The difference is substantial; during the previous visit, the land was completely vacant (raw land) with no construction activity, whereas the current visit shows the completion of foundations and the commencement of vertical element casting.
Expected next milestones
Casting of ground floor columns, and commencement of formwork and reinforcement for the ground floor ceiling.