Sawaed 109
1 Sept 2026

1 Sept 2026

0%OverallFirst visit — no previous comparison.

Engineering Report

The site was visited on September 01, 2026, and it was observed that the project is in its very early stages (leveling and excavation works). The site is currently a vacant plot where grading and preparation have commenced, with a limited presence of heavy machinery to start the primary excavation works.
Detected changes
General Site and Earthworks95%

Commencement of site leveling and initial excavation works, with visible groundwater or rainwater accumulation in parts of the site, and the presence of one excavator and a transport truck.

Concrete Structure100%

There are no existing concrete works or structural elements above ground level as of the visit date.

Site Mobilization90%

The site is surrounded by existing buildings on all sides, with limited use of adjacent areas for the storage of pipes and raw materials.

Progress reading

Visual observations align with the declared completion rate (0%), as current works are limited to site preparation, which precedes the actual commencement of structural framework components.

vs previous visit

No previous visit available for comparison

Expected next milestones

Completion of excavation works, dewatering, and commencement of blinding concrete pouring for the foundations.