1 Sept 2026
Engineering Report
Detected changes
Commencement of site leveling and initial excavation works, with visible groundwater or rainwater accumulation in parts of the site, and the presence of one excavator and a transport truck.
There are no existing concrete works or structural elements above ground level as of the visit date.
The site is surrounded by existing buildings on all sides, with limited use of adjacent areas for the storage of pipes and raw materials.
Progress reading
Visual observations align with the declared completion rate (0%), as current works are limited to site preparation, which precedes the actual commencement of structural framework components.
vs previous visit
No previous visit available for comparison
Expected next milestones
Completion of excavation works, dewatering, and commencement of blinding concrete pouring for the foundations.