GARDEN 106
6 May 2026

Sawaed Real Estate Al Rawdah 106 Project

28%Overall▲ +3% · vs previous visit

Engineering Report

Site visit report for the Sawaed 106 project dated May 6, 2026. The site is in an advanced stage of the concrete structure phase and the beginning of masonry work. There is a notable discrepancy between the entered digital data (0%) and the visual reality, which indicates the completion of significant portions of columns, slabs, and red and black brickwork.
Detected changes
Concrete Structure100%

Completion of pouring several columns and slabs (Hordi system) across various floors, with ongoing formwork and reinforcement for the upper levels.

Masonry Works100%

Commencement and execution of extensive sections of internal and external walls using red clay bricks and black cement blocks, with additional block supplies staged on-site.

Initial MEP Rough-ins90%

Installation of vertical plumbing (drainage pipes) and electrical conduits embedded within the concrete slabs.

General Site100%

The site is constructionally active with staged building materials (cement, bricks, steel), perimeter fencing, and project signage in place.

Progress reading

There is a conflict between the recorded completion rates (0%) and the visual reality; the images show that concrete and masonry works have made tangible progress, far exceeding the excavation and foundation stages.

vs previous visit

Compared to the previous site visit photos, the project has progressed from the initial concrete skeleton stage to an advanced phase, including the casting of additional slabs and the intensive commencement of masonry work on the typical floors.

Expected next milestones

Completion of masonry work, commencement of plastering (rendering), and completion of initial electrical and mechanical installations.

Progress

0%OverallAverage item progress
1/5 completeavg ▲ +3%
Excavation Works
0%
Concrete Works▲ +10%
0%
Finishing Works▲ +5%
0%
Electrical Works
0%
Plumbing Works
0%