Sawaed Real Estate Al Rawdah 106 Project
Engineering Report
Detected changes
Completion of pouring several columns and slabs (Hordi system) across various floors, with ongoing formwork and reinforcement for the upper levels.
Commencement and execution of extensive sections of internal and external walls using red clay bricks and black cement blocks, with additional block supplies staged on-site.
Installation of vertical plumbing (drainage pipes) and electrical conduits embedded within the concrete slabs.
The site is constructionally active with staged building materials (cement, bricks, steel), perimeter fencing, and project signage in place.
Progress reading
There is a conflict between the recorded completion rates (0%) and the visual reality; the images show that concrete and masonry works have made tangible progress, far exceeding the excavation and foundation stages.
vs previous visit
Compared to the previous site visit photos, the project has progressed from the initial concrete skeleton stage to an advanced phase, including the casting of additional slabs and the intensive commencement of masonry work on the typical floors.
Expected next milestones
Completion of masonry work, commencement of plastering (rendering), and completion of initial electrical and mechanical installations.