Sawaed Real Estate Al Rawdah 106 Project
Main video
Engineering Report
Detected changes
Continuation of formwork and reinforcement for columns and slabs, with newly poured concrete stairs visible and the use of metal and wooden scaffolding for slab support.
Commencement of internal and external wall construction using red clay bricks and cement blocks, with significant quantities of materials delivered to the site.
Supply of bagged cement (Yanbu), sand, and electrical/plumbing conduits, in addition to the presence of manual equipment (wheelbarrows) and stockpiled construction materials.
Progress reading
The photographs align with the reported completion rates; the progress in concrete work (35%) is evident through the completion of columns for the typical floors, and the start of finishing works (5%) is clearly visible in the commencement of masonry and the staging of plastering and plumbing materials.
vs previous visit
Compared to the previous visit, the project has progressed from the pure concrete structure stage to an advanced 'shell' stage; while masonry work was not previously visible, it now covers extensive areas of the ground and first floors.
Expected next milestones
Completion of the remaining slab casting, commencement of initial electrical and plumbing rough-ins within the constructed walls, and the start of plastering works.