6 May 2026

Sawaed Real Estate Al Rawdah 106 Project

28%Overall▲ +3% · vs previous visit

Main video

Engineering Report

Significant progress has been made on the concrete structure with a 10% increase, while masonry work (initial finishes) has commenced at 5%. Current efforts are focused on casting columns and preparing upper-level slabs, alongside the delivery and installation of red and cement blocks on the lower floors.
Detected changes
Concrete Structure95%

Continuation of formwork and reinforcement for columns and slabs, with newly poured concrete stairs visible and the use of metal and wooden scaffolding for slab support.

Masonry Works95%

Commencement of internal and external wall construction using red clay bricks and cement blocks, with significant quantities of materials delivered to the site.

Site General and Supplies90%

Supply of bagged cement (Yanbu), sand, and electrical/plumbing conduits, in addition to the presence of manual equipment (wheelbarrows) and stockpiled construction materials.

Progress reading

The photographs align with the reported completion rates; the progress in concrete work (35%) is evident through the completion of columns for the typical floors, and the start of finishing works (5%) is clearly visible in the commencement of masonry and the staging of plastering and plumbing materials.

vs previous visit

Compared to the previous visit, the project has progressed from the pure concrete structure stage to an advanced 'shell' stage; while masonry work was not previously visible, it now covers extensive areas of the ground and first floors.

Expected next milestones

Completion of the remaining slab casting, commencement of initial electrical and plumbing rough-ins within the constructed walls, and the start of plastering works.

Progress

0%OverallAverage item progress
1/5 completeavg ▲ +3%
Excavation Works
0%
Concrete Works▲ +10%
0%
Finishing Works▲ +5%
0%
Electrical Works
0%
Plumbing Works
0%