Mashrou 101
22 Jul 2025

Sawaed Real Estate Al Rawdah 101 Project

73%Overall▲ +4% · vs previous visit

Engineering Report

The project has shown significant progress in interior finishing and exterior facades; wall tiling (ceramics) has commenced in wet areas, and interior plastering works have been completed, while work continues on the exterior facades and the preparation of electrical wiring systems.
Detected changes
Exterior Facades95%

Continuation of exterior plastering works and installation of metal scaffolding around the building perimeter, with construction materials available on-site.

Interior Finishing (Ceramics)98%

Commencement of wall tile installation in kitchens and bathrooms using adhesive, noting the precision of execution and preparation of electrical openings.

Plastering and Painting Works90%

Execution of interior plastering and preparation of gypsum ceilings (suspended ceilings) in certain areas, alongside ongoing foundational works.

Electromechanical Installations95%

Installation of electrical wiring conduits and flexible piping in ceilings and walls, and preparation of distribution boxes.

Progress reading

Although the recorded overall completion rate is 0%, the photographs demonstrate actual progress in the initial finishing stages (plastering, installations, and the start of tiling), indicating a discrepancy between the documented updates and the actual field status.

vs previous visit

Compared to the previous visit, the project has progressed from the structural shell and masonry stage (visible red brick in image 21) to the comprehensive plastering phase and the actual commencement of tiling and internal installations.

Expected next milestones

Completion of floor tiling, finishing of gypsum ceilings, and commencement of the final painting stages.

Progress

0%OverallAverage item progress
1/5 completeavg ▲ +13%
أعمال الحفرnew
0%
أعمال الخرسانات
0%
أعمال التشطيب▲ +10%
0%
أعمال الكهرباء▲ +15%
0%
أعمال السباكة▲ +25%
0%