Sawaed Real Estate Al Rawdah 101 Project
Engineering Report
Detected changes
Continuation of exterior plastering works and installation of metal scaffolding around the building perimeter, with construction materials available on-site.
Commencement of wall tile installation in kitchens and bathrooms using adhesive, noting the precision of execution and preparation of electrical openings.
Execution of interior plastering and preparation of gypsum ceilings (suspended ceilings) in certain areas, alongside ongoing foundational works.
Installation of electrical wiring conduits and flexible piping in ceilings and walls, and preparation of distribution boxes.
Progress reading
Although the recorded overall completion rate is 0%, the photographs demonstrate actual progress in the initial finishing stages (plastering, installations, and the start of tiling), indicating a discrepancy between the documented updates and the actual field status.
vs previous visit
Compared to the previous visit, the project has progressed from the structural shell and masonry stage (visible red brick in image 21) to the comprehensive plastering phase and the actual commencement of tiling and internal installations.
Expected next milestones
Completion of floor tiling, finishing of gypsum ceilings, and commencement of the final painting stages.