24 Sept 2025
Main video
Engineering Report
Detected changes
Completion of white and dark gray cladding panel installation, and fitting of aluminum window frames and glass, while metal scaffolding remains in place.
Roof tiling has been completed, along with the installation of plastic water tanks and their initial piping connections.
Execution of plastering and primary wall painting, installation of floor tiling (ceramics), and routing of electrical wiring from the ceilings.
Installation of wall ceramics in wet areas (bathrooms) along with the fitting of small ventilation windows.
Progress reading
Although the recorded percentage is 0%, the photos demonstrate substantial actual progress, moving beyond the concrete structure phase into advanced stages of final finishing (facades, painting, and flooring).
vs previous visit
Compared to the previous visit's photos, the project has progressed from the completed structural frame stage to the advanced final finishing stage; previously, the facades, tanks, and interior finishes were not yet present.
Expected next milestones
Removal of external scaffolding, installation of final sanitary and electrical fixtures, and completion of external sidewalk works.