Mashrou 101
24 Sept 2025

24 Sept 2025

97%Overall▲ +12% · vs previous visit

Main video

Engineering Report

Significant progress has been observed in both exterior and interior finishing works. This includes the installation of cladding facades, windows, interior painting, and ceramic tiling, along with the completion of water tank installations on the roof.
Detected changes
Exterior Facades100%

Completion of white and dark gray cladding panel installation, and fitting of aluminum window frames and glass, while metal scaffolding remains in place.

Roof and General Site95%

Roof tiling has been completed, along with the installation of plastic water tanks and their initial piping connections.

Interior Finishes100%

Execution of plastering and primary wall painting, installation of floor tiling (ceramics), and routing of electrical wiring from the ceilings.

Sanitary Works90%

Installation of wall ceramics in wet areas (bathrooms) along with the fitting of small ventilation windows.

Progress reading

Although the recorded percentage is 0%, the photos demonstrate substantial actual progress, moving beyond the concrete structure phase into advanced stages of final finishing (facades, painting, and flooring).

vs previous visit

Compared to the previous visit's photos, the project has progressed from the completed structural frame stage to the advanced final finishing stage; previously, the facades, tanks, and interior finishes were not yet present.

Expected next milestones

Removal of external scaffolding, installation of final sanitary and electrical fixtures, and completion of external sidewalk works.

Progress

0%OverallAverage item progress
3/5 completeavg ▲ +12%
أعمال الحفر▲ +40%
0%
أعمال الخرسانات
0%
أعمال التشطيب▲ +10%
0%
أعمال الكهرباء▲ +5%
0%
أعمال السباكة▲ +5%
0%

Drone Photography