Sawaed Real Estate Al Rawdah 102 Project
Engineering Report
Detected changes
Completion of the building's structural frame with external scaffolding installed for facade work, and completion of waterproofing for the roof.
Execution of interior plastering for walls and ceilings, and the commencement of wall tiling (ceramic) in bathrooms and kitchens.
Installation of electrical wiring within conduits, mounting of distribution boxes, and rough-in of plumbing and drainage points within the apartments.
Progress reading
Although the textual data indicates 0% completion, the images confirm that the project has reached the finishing stage; excavation and concrete phases have been fully surpassed, and work is currently underway on electrical, plumbing, and plastering components, with completion rates ranging between 40% and 60% for these specific items.
vs previous visit
There is a significant difference compared to the previous visit; the site has transformed from a concrete shell structure to a plastered building, with tiling works and rooftop waterproofing now underway.
Expected next milestones
Completion of tiling works, commencement of the first coat of painting, and installation of door and window frames.