Sawaed Real Estate Al Rawdah 103 Project
Main video
Engineering Report
Detected changes
Continuation of exterior plastering and scaffolding installation for final painting, with initial finishing stages appearing on upper sections.
Execution of interior plastering and floor tiling in several units, alongside the commencement of primer coat painting.
Installation of electrical wiring in ceilings and walls, distribution box fitting, and rough-in for drainage and supply pipes in bathrooms and kitchens.
Completion of the roof slab casting and installation of upper water tanks, with construction materials still present around the site perimeter.
Progress reading
The visual evidence aligns with the reported completion rates; the tiling and plastering work reflect the 45% progress in finishes, while the wiring and piping installations are clearly visible, supporting the 60-65% progress in electromechanical works.
vs previous visit
Compared to the previous visit photos (21-26), the project has progressed from the structural and red-brick masonry stage to the plastering, tiling, and advanced internal MEP rough-in stage, indicating significant progress in the pace of internal works.
Expected next milestones
Completion of final painting works, installation of windows and doors, and commencement of sanitary ware and electrical switch installation.