Sawaed Real Estate Al-Rawdah 103 Project
Main video
Engineering Report
Detected changes
Continuation of concrete pouring using a mechanical pump for the upper floor slabs, with formwork and reinforcement visible for the roof columns and vertical axes.
Completion of external walls and internal partitions using red bricks for the first, second, and third floors is nearly finished.
Commencement of electrical rough-ins (conduit installation) and plumbing within the completed floors, with materials staged on-site.
Presence of concrete mixer trucks and a pump on-site, with relatively organized staging areas surrounding the building.
Progress reading
The visual documentation aligns with the surge in completion rates, particularly in the structural concrete works (rising from 30% to 80%), as the building has nearly reached its final height. Furthermore, the completion of masonry work across several floors accounts for the increase in the finishing completion rate to 45%.
vs previous visit
Compared to the previous visit, the project has progressed from the initial concrete frame stage (first-floor columns) to an advanced stage including the pouring of upper slabs and the completion of wall masonry, which was not visible in the previous visit's photos.
Expected next milestones
Completion of the upper annex slab pouring, commencement of internal plastering works, and intensification of plumbing and electrical installations.