Sawaed Real Estate Al-Rawdah 103 Project
Engineering Report
Detected changes
The structure is 100% complete, with all wooden formwork removed from the typical floors and the roof.
Significant progress in the construction of external and internal walls using red and cement bricks, with window openings precisely defined using concrete lintels.
Installation of PVC piping in ceilings and walls is visible, along with the preparation of electrical cable routes, reflecting a surge in completion rates (90% for electrical works).
Partial clearing of construction debris from floors, and additional brick supplies staged on the roof to complete the annexes and parapet walls.
Progress reading
The photographs align with the substantial leap in completion rates, particularly in finishing works (from 45% to 75%) and electrical installations (from 35% to 90%). The images illustrate the transition from the structural shell phase to technical installations and final interior partitioning.
vs previous visit
Compared to the previous visit, most architectural openings in the buildings have been closed, the casting of the upper annex is complete, and service installations are clearly visible across all floors.
Expected next milestones
Commencement of internal plastering works, installation of wooden door frames, and completion of waterproofing for bathrooms and rooftops.