Sawaed 105
8 Dec 2025

Sawaed Al Hamra 105 Real Estate Project

24%Overall▲ +2% · vs previous visit

Engineering Report

The project has transitioned from the raft foundation pouring stage to the vertical structure construction of the ground floor. Carpentry and reinforcement works for the ground floor columns are currently underway across the entire project area, with a heavy presence of labor and equipment on-site.
Detected changes
Concrete Structure100%

Completion of the concrete raft foundation pouring and commencement of formwork and reinforcement for the ground floor columns, including the installation of wooden shuttering and diagonal bracing to ensure column alignment.

General Site95%

Organization of the work area and stockpiling of timber and materials, with the continued presence of temporary site fencing and the mobilization of labor for carpentry works.

Progress reading

Significant progress is evident in the structural framework; while the previous visit was limited to the newly poured raft foundation, current photos show the completion of formwork for most ground floor columns, indicating readiness for the upcoming concrete pour.

vs previous visit

The fundamental difference is the transition from the ground level (raft foundation) in the previous visit (Photos 18-23) to vertical elevation with the commencement of forming the ground floor columns in the current visit.

Expected next milestones

Casting the concrete for the ground floor columns, followed by the start of formwork and reinforcement for the ground floor ceiling.

Progress

0%OverallAverage item progress
1/5 completeavg ▲ +2%
أعمال الحفر
0%
أعمال الخرسانات▲ +10%
0%
أعمال التشطيب
0%
أعمال الكهرباء
0%
أعمال السباكة
0%