Sawaed Al Hamra 105 Real Estate Project
Engineering Report
Detected changes
Completion of the concrete raft foundation pouring and commencement of formwork and reinforcement for the ground floor columns, including the installation of wooden shuttering and diagonal bracing to ensure column alignment.
Organization of the work area and stockpiling of timber and materials, with the continued presence of temporary site fencing and the mobilization of labor for carpentry works.
Progress reading
Significant progress is evident in the structural framework; while the previous visit was limited to the newly poured raft foundation, current photos show the completion of formwork for most ground floor columns, indicating readiness for the upcoming concrete pour.
vs previous visit
The fundamental difference is the transition from the ground level (raft foundation) in the previous visit (Photos 18-23) to vertical elevation with the commencement of forming the ground floor columns in the current visit.
Expected next milestones
Casting the concrete for the ground floor columns, followed by the start of formwork and reinforcement for the ground floor ceiling.