Sawaed 108
1 Sept 2026

1 Sept 2026

7%Overall▲ +1% · vs previous visit

Engineering Report

The Sawaed 108 project site was visited on 2026-09-01, where work is currently focused on the foundations and substructure phase. The photos showed slight progress in excavation and general site preparation, with ongoing work on shoring excavation sides and preparing reinforcement steel and formwork for columns at the foundation level, reflecting an overall completion rate of 7%.
Detected changes
Concrete Structure95%

Wooden formwork for columns and neck columns is visible at the footing level, with reinforcement steel prepared for pouring in parts of the site.

General Site and Excavation Works90%

Partial completion of excavation and site floor preparation, with construction equipment and materials (timber and steel) distributed across the site.

Progress reading

The photos align with the reported completion rates; the 30% completion of excavation work is clearly visible in the leveling and preparation of the project ground, while the 5% completion in concrete work reflects the actual start of carpentry and blacksmithing for foundations and neck columns, without any large-scale slab pouring yet.

vs previous visit

Compared to the previous visit, an increase in the density of formwork and the distribution of reinforcement steel within the excavation area is observed, confirming a 5% progress in excavation works, while concrete works remain in their initial foundational stages.

Expected next milestones

Pouring concrete footings, commencing column neck works, and completing waterproofing for the foundations.

Progress

0%OverallAverage item progress
0/5 completeavg ▲ +1%
Excavation Works▲ +5%
0%
Concrete Works
0%
Finishing Works
0%
Electrical Works
0%
Plumbing Works
0%