1 Sept 2026
Engineering Report
Detected changes
Wooden formwork for columns and neck columns is visible at the footing level, with reinforcement steel prepared for pouring in parts of the site.
Partial completion of excavation and site floor preparation, with construction equipment and materials (timber and steel) distributed across the site.
Progress reading
The photos align with the reported completion rates; the 30% completion of excavation work is clearly visible in the leveling and preparation of the project ground, while the 5% completion in concrete work reflects the actual start of carpentry and blacksmithing for foundations and neck columns, without any large-scale slab pouring yet.
vs previous visit
Compared to the previous visit, an increase in the density of formwork and the distribution of reinforcement steel within the excavation area is observed, confirming a 5% progress in excavation works, while concrete works remain in their initial foundational stages.
Expected next milestones
Pouring concrete footings, commencing column neck works, and completing waterproofing for the foundations.